HomeMaterials & Energy › Sonotube Calculator

Sonotube Calculator

Figure concrete for round form tubes. Enter tube diameter in inches, height in feet, how many tubes you are pouring, and a waste factor to get total cubic yards, cubic feet, and how many 80 lb or 60 lb bags to buy.

Example: with Tube diameter (inches) 12 · Tube height (feet) 4 · Number of tubes 4 · Waste factor (%) 10 → Concrete needed: 0.51 cu yd.

  • Cubic feet13.82 cu ft total (3.14 per tube before waste)
  • 80 lb bags24 bags
  • 60 lb bags31 bags

Computed by the calculator below using its default values. Change any input to see your own numbers.

Concrete needed
Cubic feet
80 lb bags
60 lb bags

Volume per tube is πr²h. One 80 lb bag of concrete mix yields 0.60 cu ft; a 12-inch tube uses one 80 lb bag per 7 inches of height, roughly.

How much concrete a form tube takes

A form tube (Sonotube is the common brand) is just a cylinder, so its volume is πr²h. The catch is units: diameter is sold in inches while height is measured in feet, and mixing them up throws the answer off by a factor of 144. This calculator converts for you — a 12-inch tube holds 0.785 cubic feet per foot of height, so a typical 4-foot deck footing takes 3.14 cubic feet, about six 80 lb bags with a little waste.

Remember to measure the full tube length, not just what shows above grade. A footing that extends 12 inches above grade but sits 42 inches deep to get below frost line is a 54-inch pour. Frost depth varies by region — check your local building department.

Bags or ready-mix?

Bagged mix makes sense up to roughly a cubic yard — that is 45 or so 80 lb bags, which is real labor to mix. Past that, short-load ready-mix usually wins on both effort and consistency. The bag counts here use the standard published yields: 0.60 cubic feet per 80 lb bag and 0.45 cubic feet per 60 lb bag. Counts round up to whole bags, and the default 10% waste covers spillage, over-excavation at the bottom of the hole, and slightly bellied tubes.

How it’s calculated

Volume per tube = π × (diameter ÷ 24)² × height, with diameter in inches and height in feet, giving cubic feet. Total = per-tube volume × quantity × (1 + waste%). Cubic yards = cubic feet ÷ 27. Bag counts round up using standard yields: 80 lb bag = 0.60 cu ft, 60 lb bag = 0.45 cu ft (manufacturer-published yields for concrete mix).

Assumes a straight cylinder — belled bases, oversized augured holes, and rocky over-dig all add concrete beyond the tube volume, which is what the waste factor is for.

Concrete per foot of tube height

Tube diameterCu ft per ft of height80 lb bags per ft
8 in0.350.6
10 in0.550.9
12 in0.791.3
16 in1.402.3
24 in3.145.2

Computed with π(d/24)² per foot and 0.60 cu ft per 80 lb bag; rounded.

Common mistakes

  • Entering diameter in feet — a '1' in the diameter box should be 12 (inches), or the answer comes out 144× too small.
  • Measuring only the above-grade height and forgetting the below-frost-line depth, which is usually most of the pour.
  • Buying exact bag counts with zero waste — an under-mixed last footing means a cold joint or a second store run.
  • Ignoring the belled or over-augured bottom of the hole, which can swallow half a bag per footing on its own.

Frequently asked questions

What is the formula for sonotube concrete volume?

Volume = π × r² × h. With diameter d in inches and height h in feet, cubic feet = π × (d ÷ 24)² × h. A 12-inch tube 4 feet tall is π × 0.5² × 4 = 3.14 cubic feet.

How many bags of concrete fill a 12-inch sonotube 4 feet deep?

About 6 bags of 80 lb mix. The tube holds 3.14 cubic feet, an 80 lb bag yields 0.60 cubic feet, and 3.14 × 1.1 waste ÷ 0.60 rounds up to 6 bags.

When should I order ready-mix instead of bags?

Around 1 cubic yard and up. That is roughly 45 bags of 80 lb mix — mixing that by hand or in a small mixer is hours of work, and pouring footings in stages risks cold joints.

Does rebar in the tube change how much concrete I need?

Not meaningfully. Two or three vertical #4 bars displace well under 1% of the tube volume, far less than normal spillage. Keep the waste factor and ignore the rebar displacement.